01Requirement
What the site needed
Capacity had to come online in blocks while the permanent building was still under construction.
A phased cabin campus with shared power and cooling plant.
02Configuration
Unit list
Reference quantities. Final scope follows the approved project schedule.
| Unit | Qty | Note |
|---|---|---|
| 40ft compute cabin | 8 | 2.4 MW reference each |
| Power cabin | 3 | MV/LV and battery |
| CDU and dry cooler | 4 | Closed loop, N+1 |
| Service cabin | 1 | Control and workshop |
03Delivery
Delivery notes
01
Block planning
Cabin positions reserved for later phases.
02
Shared interfaces
Power and cooling branches isolated per block.
03
Integrated test
Full load test across compute and cooling.